Project Fact Sheet
1. Country: Mongolia (Dornogobi/Altanshiree Soum)
2. Industry: Energy & Mining Focus on lignite coal deposits, power generation (600 MW plant), and synthetic fuel production.
3. Land area: Exploration License: 130 sq. km, Mining License: 60 sq. km
4. Regulatory Approvals: 30-year mining license for 2 billion tons of lignite coal (July 17, 2012).
5. Construction license for 600 MW power plant (August 31, 2012)
6. Financing Model: Supported by private sponsors andr private equity co-investors.